Classroom Addition

PROJECT SUMMARY

Along the southeast corner of the high school, a new set of classrooms is being constructed just north of the parking lot.  Among the set of 8 classrooms, there will be a new kitchen which will be the home of the school’s Culinary Arts program.

PROJECT UPDATE

The masonry is fully topped out and the slab on grade has just been poured.  The steel erection is finishing up shortly and we will soon have a second floor to work on. Floor build outs such as framing and MEP will be installed in the next few weeks.

PROJECT PROGRESS

Design – 100% Complete

Construction – 50% Complete